May 19, 2020

 

The regular meeting of the Barry County Road Commission was called to order via phone meeting (allowed by the Executive Order of the Governor due to COVID 19) at 7:30 A.M. by Chairman Solmes.  A telephone number with a meeting ID # was supplied to the Commissioners and the public via our website, Facebook, and posted at our gate at our location so all could participate.

 

Members present:  Solmes, Fiala, Dykstra and Managing Director Bradley Lamberg.

 

The agenda for May 19, 2020 was approved.

 

The minutes of May 5, 2020 were approved as printed.

______________________________________________________________________________

 

Motion was made and seconded to approve payroll for payment.

 

ROLL CALL:  Yeas, Solmes, Fiala, & Dykstra

Nays, None

Motion Carried

 

CHECK             NAME                                                                            AMOUNT

5/14/20                Barry County Road Commission                                    $102,766.46

______________________________________________________________________________

 

Motion was made and seconded to approve the bills for payment.

 

ROLL CALL:  Yeas, Solmes, Fiala, & Dykstra

Nays, None

Motion Carried

 

5/14/20

Check Number Vendor Name Check Amount
41136 Adam Nieland $30.00
41137 Bert Keeler $380.00
41138 Brad Lamberg $80.00
41139 Brandy Casey $80.00
41140 Brian Donnini $30.00
41142 Capital One Bank $24,298.25
41143 Carleton Equipment Co $4,578.24
41144 Carpenter Gravel Inc $2,356.68
41145 Charles Benedict $552.54
41146 Chris BeBeau $80.00
41147 City Of Hastings $605.26
41148 Consumers Energy $16.84
41149 Culligan Water Conditioning $73.50
41150 Dic Craven $53.53
41151 Douglas Peck $80.00
41152 Gary Vandecar $604.71
41153 Gerald Cisler $552.54
41154 Grand Valley Concrete Products $3,001.00
41155 H.S.V. Redi-Mix $5,160.55
41156 Hall’s Septic $600.00
41157 Hammersmith Equipment Company $3,025.00
41158 Hastings Ace Hardware $8.49
41159 Jack Kineman $276.28
41160 Jake Welch $80.00
41161 Jim Raulston $92.00
41162 Kelly Fuels Inc $137.18
     
     
Check Number Vendor Name Check Amount
41163 Kendall Pranshka $276.28
41164 Lakeland Asphalt Corp $364,224.79
41165 Larry Maupin $552.54
41166 Lawrence Barry $270.00
41167 Lincoln National Life Ins $211.15
41168 Linda Miller $264.00
41169 Mark Weeks $340.00
41170 Patricia Wolf $276.28
41171 Purity Cylinder Gases Inc $341.27
41172 Randy Roush $64.00
41173 Rex Ferris $84.50
41174 Robert Baines $53.53
41175 Robert Nagel $552.54
41176 Robert Richardson $80.00
41177 Robert Slocum $552.54
41178 Scott Bond $80.00
41179 Scott Schantz Jr. $30.00
41180 SME Inc. $4,952.20
41181 St. Regis Culvert Inc $5,040.00
41182 Superior Asphalt Inc $3,360.00
41183 The Huntington National Bank $500.00
41184 Tom Chaffee $107.04
41185 Tractor Supply Company $59.99
41186 Varipro Benefit Administrators $891.00
41187 Walker, Fluke, & Sheldon PLC $9,000.00
41188 Wayne Roush $276.28
Total $439,272.52

______________________________________________________________________________

 

Motion was made and seconded to request reimbursement in the amount of $10,000.00 for payment made during the period of July 1, 2019 through June 30, 2020 to a licensed professional engineer employed by this Commission, in accordance with Sec. 12(2) of Act 51.

 

ROLL CALL:  Yeas, Solmes, Fiala, & Dykstra

Nays, None

Motion Carried

______________________________________________________________________________

 

Motion was made and seconded to adopt the COVID 19 Preparedness and Response Plan.

 

ROLL CALL:  Yeas, Solmes, Fiala, & Dykstra

Nays, None

Motion Carried

 

 

 

 

 

 

 

 

 

 

 

 

Motion was made and seconded to accept Barry Township Resolution for Road Work.

 

ROLL CALL:  Yeas, Solmes, Fiala, & Dykstra

Nays, None

Motion Carried

 

At the regular meeting of Barry Township Board, held on May 12, 2020 the following Resolution was adopted.

 

There came before the board the following matter:

 

Now THEREFORE BE IT RESOLVED that the Township of Barry hereby agrees to the following road work to be done in 2020.  Road work requested:  Streets in Delton.  Total Cost:  $160,084.00.  We are requesting to make payments for said roadwork.  Payments are as follows:

 

2020    $40,084.00

2021    $40,000.00

2022    $40,000.00

2023    $40,000.00

 

Dust Layer:  $13,500.00

 

Motion by Lee Campbell second by Debra Knight to adopt this resolution #20-05.

______________________________________________________________________________

 

Motion was made and seconded to accept Thornapple Township Resolution for Road Work.

 

ROLL CALL:  Yeas, Solmes, Fiala, & Dykstra

Nays, None

Motion Carried

 

Re:  Thornapple Township Road Program for 2019

 

Project                                                             Township Funding

Dust Control                                                   $15,000*

 

This amount is to cover two (2) separate standard dust control applications to all Thornapple Township gravel roads except for the gravel sections of Moe Road.  Moe Road will receive three (3) double applications of dust control.  All dust control to be applied at the convenience/discretion of the Barry County Road Commission (BCRC).

 

*Of this $15,000 amount, $2,100** will come from a Special Assessment to the residents of Moe Road to fund two (2) of the three (3) double applications of dust control.

 

**It is understood that this number could fluctuate dependent of the cost of the dust control product(s) and whether or not a third application is necessary.

______________________________________________________________________________

 

Motion was made and seconded to accept Orangeville Township Resolution for Road Work.

 

ROLL CALL:  Yeas, Solmes, Fiala, & Dykstra

Nays, None

Motion Carried

 

 

 

 

 

 

 

 

Orangeville Township Resolution:

 

England Drive repairs, Trustee Ribble presented 2 options per Barry County Road Commission.  Option 1 cost of $23,000, Option 2 cost of $50,000.  It was noted that $7,082 was already in the 4-year payment plan budget for England Drive and costs of options would be reduced by that amount.

 

Motion Trustee Ribble to authorize repave project England Drive north of Marsh Road, 0.41 miles per Option 2 from BCRC.  Total cost of approximately $43,000.

______________________________________________________________________________

 

Motion was made and seconded to accept Village of Middleville Resolution for Road Work.

 

ROLL CALL:  Yeas, Solmes, Fiala, & Dykstra

Nays, None

Motion Carried

 

Approved to chip seal the following streets:

 

Minsthre Drive 933’ x 26’ = 24,258 sqft

Oak Meadow Drive 2160’ x 27’ = 58,320 sqft

Towne Center Drive 2013’ x 38’ = 76,494 sqft

Lloyd Court 1265’ x 26’ = 32,890 sqft with a 70 ft cul-de-sac

Oak Wind Court 309’ x 25’ = 7,725 sqft with a 68 ft cul-de-sac

Oak Brook Court 280’ x 25’ = 7,000 sqft

Oak Hill Court 684’ x 25’ = 17,100 sqft with a 68 ft cul-de-sac

 

Also the start point for west main would be just west of Russell heading west to Robin Street.  When you cross M-37 I will leave up to you guys on the stop and start points.  I know at some point this summer MDOT will be resurfacing M-37 through Middleville.  To my understanding this will include all intersection to the break points.

______________________________________________________________________________

 

The Board discussed the cost of the sand and sand bags being supplied by the Barry County Road Commission for residents that high water is threatening their structures.

______________________________________________________________________________

 

Jake Welch, Director of Operations, spoke to the Board about timber harvesting in the Doster Pit.  The BCRC is having a contractor crush gravel this year in Doster Pit and there are trees in the way that need to be removed.  There are also Walnut trees that every 10 – 15 years we thin out.  Mark Bishop with Quality Forest Management took bids on the sale of the Hardwood and Walnut trees.

 

Bidder                                                Hardwood Trees                   Walnut Trees

Buskirk Lumber                                  $1,950                                     $8,250

SanInocencio Timber Products           $3,000                                     $11,200

 

Motion was made and seconded to award Timber Harvesting in the Doster Pit to SanInocencio Timber Products as high bidder.

 

ROLL CALL:  Yeas, Solmes, Fiala, & Dykstra

Nays, None

Motion Carried

______________________________________________________________________________

 

Meeting adjourned at 8:15 A.M.

 

 

 

________________________________                   __________________________________

Secretary                                                                     Chairman